Project Timeline for Primary Project

March 29th -

  • Apply for funding
  • put elements into Maya
  • Apply Textures
April 5th
  • Send Maya documents to Holton,
  • observe process of putting objects in Virtools
  • write narrative and
  • create survey
  • complete IRB application and gather participants

April 12th

  • Conduct test runs
  • Make any revisions
  • document process

April 19th

  • conduct participant sessions
  • analyze results
  • document process
  • complete poster

April 26th

  • wrap up project
  • complete write-up